Shizuoka Governor Yasutomo Suzuki said Tuesday that he will allow construction to begin on the Maglev Chuo Shinkansen line through Shizuoka Prefecture [1].

This decision removes a primary political and environmental hurdle for the high-speed rail project, which aims to connect Tokyo and Nagoya. The approval follows the completion of resident briefing sessions and an agreement on environmental protection measures [2].

Suzuki said that JR Central has demonstrated a commitment to preserving the natural environment and providing thorough explanations to local residents [1]. The governor said that the project must now move forward quickly to ensure early completion [2].

However, JR Central President Shunsuke Niwa said that the project faces significant hurdles. Niwa said he believes the construction will be more difficult than previously anticipated [1].

While previous estimates suggested the construction period for the Shizuoka section would be approximately 10 years [3], Niwa said that the work may now take longer than that original timeframe [1]. The increased complexity of the engineering requirements suggests that the initial 10-year window may no longer be realistic [1, 3].

Despite these warnings, Niwa said the company will put forth every effort to achieve an early opening [1]. Current projections suggest the Shizuoka section of the Maglev line will not open until 2036 or later [4].

JR Central has demonstrated a commitment to preserving the natural environment.

The approval marks a critical diplomatic victory for JR Central, ending years of deadlock over water rights and environmental concerns in Shizuoka. However, the admission that construction is more difficult than expected suggests that the project's timeline is slipping. The shift from a 10-year estimate to a potential extension indicates that technical challenges in the region's geography may outweigh the political progress, pushing the operational date further into the next decade.